Description
There are three definitions of a subdivision as follows:
-
When
1 or more lots are divided off a residual lot, such as a
parent dividing off a small lot for their child to build a
home.
-
When
a property owner wishes to divide an existing lot into 2
or more individual lots.
-
When
a property owner is constructing a second residence on an
individual lot. (Note: Some municipalities do not
allow this practice.)
Subdivisions
- Additional Requirements
In addition to following the standard sewage
permitting process, there are some additional steps
required when applying for an on-lot sewage septic system
permit for a subdivision. These additional requirements
are as follows:
-
The
permit fee changes. See the Fee
Schedule to see the permitting fees associated with
subdivisions.
-
A
Visual Inspection must
be done if there is a residence on the residual parcel in
the subdivision.
-
If
any type of Alternate System
is utilized, the SEO must find a second site on the
lot (or lots), or there must be a maintenance agreement in
place for that/those specific lot/lots.
-
Planning
Modules are required for all subdivisions if there is any
perc testing done on any lot in the subdivision.
DEP
Planning Module Information
Click here
to go to the DEP web page that contains detailed information
related to planning modules.
Instructions
for Subdivision Permits
Click here to view detailed instructions
for applying for a sewage permit for a subdivision.
|